Sample — fictional building, not a client project. For method and format only.
Sample deliverable

Sample — fictional building, not a client project

This page shows how we lay out a filing package, a coordination study and a capacity summary. The building, numbers and equipment are made up. Nothing here was sealed, filed or built.

Sample Tower (fictional)
000 Example Street, New York, NY (fictional address) · Mixed-use, 24 stories (fictional)
Utility service 480Y/277 V, 3-phase, 4-wire · Owner: "Example Owner LLC" (fictional)
Part 1 · Sample

Plan review package excerpt

Sample one-line diagram: 3000 A main switchboard, fire pump tap, two paralleled 750 kW generators, two transfer switches, and three 300 kVA UPS modules in N+1 with maintenance bypass. Fictional building.
Figure 1. Sample — fictional building, not a client project. One-line excerpt to 2nd-level overcurrent protection, with the UPS system on the optional standby transfer switch.

Service kVA per NYC Electrical Code §110.2(C)

Sample — fictional building. Service kVA calculation.
Service disconnectAmps countedkVA at 480 V
MSB main, 3000 A3,000 A2,494.2
Fire pump disconnect (100 hp, FLA 124 A × 125%)155.0 A128.9
Total service capacity2,623.0 kVA

kVA = √3 × 480 V × A ÷ 1000. Sample values.

Findings (sample)

  • 2,623.0 kVA ≥ 1000 kVA: Electrical Plan Review required (§110.2(B)(1)).
  • Service equipment ≥ 2000 kVA: drawings show the room cooling method (1 RCNY §4000-01(b)(1)(iii)(M)).
  • Two 938 kVA generators, each under 1000 kVA, within a 1000 kVA-or-larger submission: one-line shows their connection to normal service, frame grounding and neutral bonding (4-pole transfer switches) (§4000-01(b)(1)(iii)(S)). The paralleled plant totals 1876 kVA, so we also show the generator room layout and confirm the approach with the DOB examiner.
  • Generator redundancy: sample standby demand is 700 kW, so either generator can carry it alone (N+1). Each transfer switch has its own feeder breaker on the generator paralleling bus (600 A to ATS-1, 800 A to ATS-2), so a fault on one emergency feeder doesn't take out the other.
  • Available fault current shown at the service entrance and where interrupting ratings change (§4000-01(b)(1)(iii)(N)).
  • UPS system shown as part of the installation (§110.2(B) lists UPS systems): three 300 kVA modules in N+1, so 600 kVA stays available with any one module out of service, plus a maintenance bypass to service the system without dropping the critical load.
  • Selective coordination statement on the drawing; PE coordination report filed before inspection, including the ATS-2 to UPS input breaker, the module breakers and the bypass device.
Part 2 · Sample

Coordination study excerpt

Sample time-current curves for a branch breaker, a feeder and the main, with no overlap. Fictional building.
Figure 2. Sample — fictional building, not a client project. Schematic curves, not manufacturer data.

Settings table (sample)

Sample — fictional building. Recommended settings.
DeviceRatingLong timeShort timeInstantaneous
MSB main3000 A LSIG1.0 × In, band 44 × In, 0.3 sOff
DP-1 feeder800 A LSI1.0 × In, band 35 × In, 0.2 sOff
Branch225 A TMFixed—Fixed

Summary of findings (sample)

  • Main, feeder and branch curves do not overlap across the available fault range.
  • Emergency-system transfer switch feeders coordinated with the generator main.
  • One existing feeder device cannot coordinate with its downstream branch; replacement recommended.
Part 3 · Sample

Capacity summary

Sample Annex (fictional), a 1960s six-story building on a 1200 A, 208Y/120 V service. The board wants heat pumps, eight EV chargers and electric domestic hot water.

Sample — fictional building. Capacity summary.
ItemkVABasis (sample)
Existing service capacity, 1200 A at 208 V432√3 × 208 V × 1200 A
Existing demand32512-month peak demand from utility data, plus 25% margin
Heat pumps (added)180Manufacturer data at design heating condition
EV chargers, 8 × 7.2 kW, managed (added)35Load management limit
Electric water heating (added)45Heat pump water heater with backup elements
Projected demand585Exceeds existing service by about 153 kVA

Options (sample)

  1. Partial electrification on the existing service. Heat pumps sized for part of the heating load (about 105 kVA), existing boilers kept for peak days, EV charging and water heating deferred. Projected demand about 430 of 432 kVA: it fits, with no margin.
  2. Upgrade the service to 2000 A at 208 V (about 720 kVA). Covers the full plan. Under 1000 kVA, so §110.2(B) plan review is not triggered. Requires a utility service request and load letter.
  3. Add a second service. Usually costlier; considered only if the utility can't upgrade the existing one.

Sample values for format only. A real study uses the building's actual demand data and equipment.

Part 4

What you get, and when

  • Task order confirming scope, fixed fee and what DOB will need
  • Sealed drawings: one-line, plan view, room layout as required
  • Service kVA calculation and fault current values
  • EPR intake and cover sheet, filed with DOB
  • Objection responses and amendments through approval
  • PE selective coordination report before inspection

11business days from a complete submittal package (standard turnaround)

5business days for a complete resubmittal

Want this for a real job?

Send the equipment list and a one-line sketch. We'll confirm the scope and quote a fixed fee.

jstrafer@straferengineering.com
Site visits in all five boroughs and across New York State.