What EPR is
Electrical Plan Review (EPR) is DOB's approval step for large and high-voltage electrical installations. It replaced the Electrical Advisory Board, which DOB eliminated in July 2019. DOB electrical plan examiners now review the filings.
The five triggers
Under the 2025 NYC Electrical Code §110.2(B), an "installation" means service equipment, transformers, UPS systems, generators, generator paralleling equipment, or other sources such as energy storage, fuel cells, PV, DC or AC microgrids, cogeneration and stationary batteries. Approval is required before building:
- A new installation totaling 1000 kVA or larger.
- Any change to an installation of 1000 kVA or larger, up to and including 2nd-level overcurrent protection, unless it was approved as "future".
- An addition that brings the total to 1000 kVA or larger.
- Added equipment in a room that affects clearances around a 1000 kVA-or-larger installation.
- A new or revised installation above 1000 V AC or 1500 V DC, regardless of kVA.
Two exceptions: fire alarm service taps, and the addition of one 2nd-level overcurrent device of 200 A or less.
Note on voltage: the older 2011 code used 600 V. The 2025 code uses 1000 V AC / 1500 V DC.
How DOB counts kVA
§110.2(C) sets the method. For a utility service, add the maximum ampere ratings of each service disconnecting means and calculate kVA at the operating voltage. Include all new and existing disconnects on the common service entrance. Count a fire pump disconnect at 125% of the fire pump's full-load amps. For a transformer, UPS, generator or other source, use its maximum kVA output rating.
Example: a 3000 A main at 480 V is √3 × 480 × 3000 ÷ 1000 ≈ 2494 kVA. See the sample calculation.
What the package contains
1 RCNY §4000-01 requires a one-line diagram, a plan view and, if required, an equipment room layout. Among the specific items:
- New work clouded; existing work identified.
- Plan view to scale from the point of service entrance, with service equipment arrangement and clearances.
- Location of the electric service room relative to surrounding areas, and the means of egress.
- Room cooling method where service equipment totals 2000 kVA or larger.
- Available short-circuit current at the service entrance and where interrupting ratings change; series ratings where used.
- A statement that fuses and breakers are coordinated for selective short-circuit protection.
- A one-line to the 2nd level of overcurrent protection with ratings, make, type, interrupting ratings and wire sizes, plus frame and trip sizes.
- All voltages shown; transformers shown properly grounded.
- Generator connection details, and a room layout for generators of 1000 kVA or larger.
Before electrical inspection, a PE must file a selective coordination report with time-current curves, short-circuit calculations and a summary of findings. That PE may be different from the applicant. If the installation differs from the approved drawings, as-built amended drawings must be filed before inspection.
Who files, and how
Submissions must come from a New York State licensed and registered PE or RA. The EPR cover sheet is signed by the building owner or authorized representative and signed and sealed by the PE or RA. Since September 1, 2026, initial filings and post-approval amendments go through DOB's EPR Intake Form, one application per submission. DOB then emails the job number, fee and instructions.
Fees: $650 for an initial filing; $130 for a post-approval amendment.
Which code edition
New EPR filings since December 21, 2025 are reviewed under the 2025 NYC Electrical Code. Work approved with a permit under the 2011 code before that date stays on the 2011 code for inspection.